According to information transmitted by the representatives of the National Airports Company Bucharest (CNAB), the order to start construction works for a new parking lot at the Henri Coandă Bucharest International Airport has been issued.
The investment is a significant one. The new parking lot will have an area of 20,265 square meters and will involve extensive work.
The execution period, from the start of work, is six months. During this time, it is expected that 662 new parking spaces will be created. Of these, there will also be 66 that will have the necessary infrastructure for the installation of electric car charging devices.
The value of the contract is 14,894,588.71 lei (without VAT). It was awarded to the association SSAB AG - BEMEL AG - SSAB INTERNATIONAL ELECTRIC, informs antena3.ro
Comentários